External corrosion direct assessment (ECDA) surveys
CIPL, CAT, DCVG, ACVG and other field surveys to assess pipeline protection, locate coating defects and prioritise locations for direct examination.
The ECDA process
ECDA follows the four-step method of NACE SP0502. We carry out the indirect inspection surveys, then classify and prioritise the indications for direct examination.
Pre-assessment
Pipeline records, coating type, CP history and route conditions are reviewed to divide the line into ECDA regions and choose the survey tools.
Indirect inspection
At least two complementary surveys are run over each region to measure protection levels and find coating defects.
Direct examination
Indications are classified and prioritised, and the most significant are excavated to inspect the coating and pipe surface.
Post-assessment
The results confirm how effective the assessment was and set the interval for the next one.
Survey methods
Close interval potential logging (CIPL)
We log pipe-to-soil potentials at short intervals along the route, with current interruption, to build a profile of protection levels between test stations.
Direct current voltage gradient (DCVG)
Voltage gradients measured at ground level locate coating defects and indicate their size and whether they are corroding.
Alternating current voltage gradient (ACVG)
A signal applied to the pipeline produces voltage gradients at coating defects, which an A-frame and receiver pinpoint from the surface.
Current attenuation testing (CAT) with A-frame
Signal current measured along the pipeline shows sections where current is lost through poor coating. A-frame readings then pinpoint the faults.
On/off potential survey
Potentials are recorded with the CP current switched on and momentarily interrupted, using synchronised current interrupters, so the IR drop can be separated from the polarized potential.
Coating conductance survey
Current and potential measurements between test points give the conductance of the coating: a measure of its overall condition and of the protection current a section will need.
What you receive

- Potential profiles along the surveyed route
- GPS-referenced locations of coating defects and other indications
- Severity classification of each indication
- A prioritised list of locations for direct examination, with recommendations
Planning a cathodic protection project?
Tell us the asset, location and project stage. Our engineers will reply by email.
